Correlation calculation between project complexity, measured by their arcs and nodes network, and project performance, measured using the earned value method
Main Article Content
Sent:
Feb 21, 2020
Published: Jul 31, 2020
Published: Jul 31, 2020
Abstract
The usefulness of measuring project complexity is raised, and a comparative analysis between a project’s complexity, measured using the project schedules, vs a project´s performance is provided. The use of nodes and arcs of the work schedule of a project to assess its complexity is explained, adopting the methodology and formulas proposed by several researchers, producing their respective complexity indexes. In turn, earned value method to measure the performance of a project (performance index) is explained and finally its comparison is made using the Pearson correlation coefficient.
Keywords
Project complexity, earned value, complexity index, schedule performance index.Downloads
Download data is not yet available.
Article Details
How to Cite
Polo A, H., & Palma, Y. (2020). Correlation calculation between project complexity, measured by their arcs and nodes network, and project performance, measured using the earned value method. I+D Tecnológico, 16(2), 120-124. https://doi.org/10.33412/idt.v16.2.2840